Question: A can do \displaystyle \frac{1}{2} of a piece of a work in 5 days, B can do \displaystyle \frac{3}{5} of the same work in 9 days and C can do \displaystyle \frac{2}{3} of the work in 8 days. In how many days can three of them together do the work? (a) 3 days (b) 5 days (c) \displaystyle 4\frac{1}{2} days (d) 4 days |
Ans: (d) 4 days
Explanation:
Step 1: Determine the total time taken by A, B, and C to complete the work individually
Total Work = 1 part
A can do \displaystyle\frac{1}{2}​ of the work in 5 days.
Total time for A to complete the work = 5 \times 2 = 10 days.
B can do \displaystyle\frac{3}{5}​ of the work in 9 days.
Total time for B to complete the work = 9 \times \displaystyle\frac{5}{3} = 15 days.
C can do \displaystyle\frac{2}{3}​ of the work in 8 days.
Total time for C to complete the work = 8 \times \displaystyle\frac{3}{2} = 12 days.
Step 2: Total Work
Let the total work = LCM of 10,15 and 12 = 60 units.
Step 3: Calculate the 1-day work of A, B, and C
A’s Efficiency = \displaystyle\frac{60}{10} = 6 units/day.
B’s Efficiency = \displaystyle\frac{60}{15} = 4 units/day.
C’s Efficiency = \displaystyle\frac{60}{12} = 5 units/day.
Step 4: Combined work rate of A, B, and C
Combined Efficiency = 6 + 4 + 5 = 15 units/day.
Step 5: Time taken to complete the work together
The total time required to complete 60 units is:
\text{Time} = \displaystyle\frac{\text{Total work}}{\text{Combined work rate}} = \displaystyle\frac{60}{15} = 4 \, \text{days}.Final Answer:
The three of them together can complete the work in 4 days.
Option (d): 4 days.
Join Us
Join the discussion and ask any question of maths and reasoning directly to us and other like-minded user just like you!