A can do 1/2 of a piece of a work in 5 days, B can do 3/5 of the same work in 9 days and C can do 2/3 of the work in 8 days. In how many days can three of them together do the work?
A, B, and C together can complete the work in 4 days. Learn how to calculate their combined work rate in this step-by-step solution.